Score the demonstrated arrangement, not the sales presentation. Use whole-number scores and document the evidence supporting every rating.

Raw scoreMeaning
0No usable evidence, or demonstrated inability to meet the criterion
1Weak; predominantly an assertion or material unresolved operational deficiency
2Some credible capability, but not all requirements for 3 are met
3Meets every agreed minimum requirement for the criterion
4Meets 3 and demonstrates substantial, verified advantages, but not every requirement for 5
5Meets every predeclared stretch requirement with suitable verification

What evidence limits should apply?

Apply an evidence ceiling to prevent documentation quality from being confused with operational proof.

Evidence statusDefinitionMaximum score
U — UnavailableMissing, unusable, stale or materially mismatched evidence0
A — AssertionMarketing statement, untested demonstration or unsupported supplier attestation1
D — DocumentedRelevant procedures, commitments and supporting records reviewed, but not independently tested3
V — VerifiedRelevant primary records independently checked, buyer-tested performance, or an executed obligation verified for the claim being scored5

An executed contract can verify an obligation; it does not verify future delivery performance. A software demonstration can verify a feature; it does not establish that every dispensing partner supplies complete events.

For each criterion:

Final criterion score = lower of raw capability score and evidence ceiling

Weighted points = criterion weight × final criterion score ÷ 5

Total selection score = sum of weighted points

Also report evidence coverage: the total weight of criteria supported at D or V level. Use it as disclosure, not as a second multiplier that double-penalises missing evidence.

What decision follows from the result?

ResultRecommended decision
Any gate FAILExclude the proposed arrangement until the underlying issue is remedied and re-reviewed.
Any gate HOLDKeep unranked. Resolve the question before a live pilot or supply commitment.
All gates pass; 80–100; every criterion at least 3Eligible for final award review, subject to required contracts, implementation acceptance and specialist sign-off.
All gates pass; 70–79Negotiate or run a bounded pilot. Require at least 3 on fulfilment, continuity, state readiness and workflow before live deployment.
All gates pass; below 70Redesign or shortlist another arrangement.
Any later gate deteriorationSuspend reliance on the previous approval and initiate the agreed clinical/legal continuity process.

A score above 80 is not an instruction to purchase. The committee must still reject an arrangement that breaches a predeclared affordability, exposure or other mandatory limit.

Explore the table row by row

A working view of the research

0

Meaning
No usable evidence, or demonstrated inability to meet the criterion

Sources cited on this page

    See the section’s source register for the research context.

    Section sources →